The correct answer is option (F)In PERT, another path could become critical.
Explanation:
Solution
From the given question, the following statement is true, If In PERT another path could become critical.
Now,
Depending on the standard deviation of another path or way, even with a shorter duration or period, the higher degree of variability could bring about the change in a critical path or result in the critical path being changed.
The answer is C
Explanation: