Given the following information regarding a project involving an initial public

Given the following information regarding a project involving an initial public offering (IPO):
Activities Description Duration (weeks) Predecessors
a. Check feasibility 3 β€”
b. Determine funding 1 β€”
c. Find possible banks 3 a
d. Select two possible 4 a
e. Interview two banks 4 b
f. Analyze funding costs 5 b
g. Determine chance of success 2 c ,e
h Sign contract 3 f
a) Draw the network.
b) What is the critical path?
c) Calculate the float for each activity.
d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extra weeks?
Show Answers
alanihuling
alanihuling
4,8(18 marks)
The answer is B 141 billion

Popular Questions about the subject: Business

What key quality elements should Columbia Sportswear emphasis...
Business
20.03.2023 08:49
Items used to produce other goods and services are called...
Business
14.06.2021 03:06
The 1999 master tobacco settlement agreement between the states and the tobacco...
Business
15.06.2022 22:59
In the page layout view, the ruler measurement is displayed in...
Business
29.07.2020 12:35
Which accurately demonstrates the progression of technology...
Business
03.02.2020 02:40

New questions by subject

What word would be the adjective form of the verb attract? A. attractively...
English
06.05.2021 04:28
WILL MARK BRAINLIEST JUST PLS HELP ME...
Mathematics
20.05.2021 09:10
I need help on this...
Mathematics
21.09.2020 08:48
100 PTS What is the value of x?...
Mathematics
17.12.2020 22:36
HELP ASAP 3 attached...
Mathematics
16.12.2022 09:22
There are 15 counters. One-third of the counters are yellow. How many counters...
Mathematics
29.03.2022 01:27
PLS HELP I NEED HELP ASAP PLS AND TY ILY IF U DO...
History
14.05.2023 04:26
#
#
#
#
# #

We expand our knowledge with many expert answers